Stuttgart 21 rail project to cost extra €1.1 bln

Author thumbnail
Stuttgart 21 rail project to cost extra €1.1 bln
Photo: DPA

The controversial railway development Stuttgart 21 is expected to cost around €1.1 billion more than originally planned, Deutsche Bahn said on Wednesday. The figure pushes the project's final price tag to at least €5.6 billion.

Advertisement

Stuttgart 21 aims to transform the Baden-Württemberg state capital into a major European transport hub by laying 57 kilometres of new track and rebuilding the city’s main train station underground.

Germany's national railway operator Deutsche Bahn previously estimated it would cost around €4.5 billion, but now the extra billion has to be found.

“The economic viability of the project is decreasing, but it will not go negative,” said Deutsche Bahn manager Volker Kefer.

He added that while there was a chance that this figure could increase further, there was also a chance that the costs could be cut by as much as €200 million.

Baden-Württemberg state premier Winfried Kretschmann said that if Deutsche Bahn's estimation was correct, the company would have to pay the difference themselves. “This is due to planning errors by the Bahn,” he said.

Criticism of the massive rail project has come from many sides, including environmentalists who voiced concern about the effect the building work could have on the area. Violent protests rocked the southwestern city in 2011 after the police cleared a demonstrators' camp.

DPA/DAPD/The Local/jcw

More

Join the conversation in our comments section below. Share your own views and experience and if you have a question or suggestion for our journalists then email us at [email protected].
Please keep comments civil, constructive and on topic – and make sure to read our terms of use before getting involved.

Please log in to leave a comment.

See Also